Network Rail re-signalling
Lankelma worked with Network Rail for part of the Cardiff area signal renewal works.
  
UXO testing at Farringdon Station
Lankelma undertook 72 combined magcone tests in 4 shifts of 12hrs. With UXO data being assessed on site, the piling crews could start work without delay.
 
10mph at Medge Hall
Site works in the 4-foot were undertaken using UK12 - the rail truck, whilst UK15 undertook testing in the soft fields adjacent, using UK15 - the track truck.
   
Embankment nr Diss
6m high and constructed on a peat bog - these underlying soil conditions were causing subsidence. The ground investigation consisted of piezocone tests, MOSTAP sampling and the installation of 8 vibrating wire piezometers.
 
Railway bridge on the CTRL
An interesting challenge, there was no access in or out and the site was full of piles that could not be touched!
 
Rolsvoy bridge in Norway
The installation of vibrating wire piezometers to continually give readings of the stresses on the piers before, during and after rail freight crosses the bridge. CPTs to provide information on soil conditions below the piers.
 
Embankment ground investigation, Charing, Kent

The first purpose was to actually look at the material of the subsiding embankment along its whole stretch. The second purpose of the investigation was to carry out some work for a Network Rail research project.
 
Horizontal testing in the London Underground
CPTs were not required to be taken vertically down as usual but at a nearly horizontal incline through the sidewall of an underground tunnel.  This was an interesting challenge that finally led to the development of UK10.
  
Emergency SI..
UK14's 6m reach enabled tests to be carried out from one track.  This proved to be extremely useful as there were a number of other activities being carried out at the same time.
 
Platform 5, Victoria Station
Angled testing for soil conditions under a concrete column, performed over a trial pit.
    

Click here
 to download our rail capability statement 5.22MB.
    
   
A selection of completed rail site investigations:


   Project                  Client                       Purpose
Thrandeston Bog Dyer & ButlerEmbankment investigation on soft ground
Bromley Edmund Nuttall Embankment investigation used in conjunction with GPR
Felixstowe Soil Mechanics Site investigation for the design of a new track
Nuneaton Atkins, ESL Site investigation for the foundation design for new signals
Chalfont & Latimer to Chesham Metronet Large project investigating all the earthworks for this section of the Metropolitan line
Lymington Edmund Nuttall Investigation for the retaing wall next to the rail line
Rugby Stn remodelling Soil Mechanics Large investigation for the remodilling of Rugby stn and the surrounding lines
Billington Embankment White Young Green Embankment Investigation from the toe
Hollingbourne Embankment Edmund Nuttall Embankment Investigation
Tamworth    Balfour Beatty Site investigation for earthworks' retaining structures
Crew to Kidsgrove electrification Carillion/Atkins  Electrification of a branch line to take west coast main line traffic.  Data used for embankment assessment, trackbed assessment and design for new signals and OHE gantries
Rugby Scott Wilson/ Geotechnics  Resignalling work.  Data used for foundation design for new signal gantries.
Church Brampton Birse/
Bachy Soletanche
Verification testing of lime cement columns for strengthening of a rail embankment.
Browney Curve, Durham May Gurney Geotechnical Embankment site investigation.  Data was used to design a new drainage system.
London Underground Tunnel Assessment 1 TubelinesSpecialilsed testing inside running tunnels.  6 sites tested. Pressuremeter testing, sampling, installation of piezometers
Marple Edmund Nuttall Site investigation for an embankment problem. 
CTRL 440    Balfour BeattySite Investigation mainly for new trackbed.  Data used to verify trackbed quality.
London Underground Tunnel Assessment 2 Tubelines Specialised testing inside running tunnels.  5 sites, pressurementer testing and installation piezometers
CTRL 103  Kier Nuttall joint venture A number of site investigations mainly not on rail.  A tunnel investigation with UK10.
CTRL  310     Site investigation using a specially adapted frame to look at the depth of solution features in a cutting for soil nail design.
Temple Mills Depot   
Fitzpatrick/
CET Group   
Site investigation for a new rail depot foundation design.
Thrandeston Bog    First Project/
ARUP   
Embankment site investigation.  CPTs & sampling.  Instrumentation installed. Work carried out on track and at toe of embankment.
New Mistley    First Project/
Atkins
Embankment site investigation carried out on the rails.
Castly Embankment Atkins Site investigation at toe of the embankment.
Regents Park    London Underground Limited Research project with LUL carrying out seismic CPTs , sampling and installing instrumentation.
Medge Hall    May Gurney Rail Site investigation for an embankment problem
 
 
                                                                                       



Rail Projects



contact Lankelma
tel: +44 (0)1797 280050

or use our contact form